Nordic - Baltic Hydrogen Corridor

The goal of the project “Nordic-Baltic Hydrogen Corridor” is to develop hydrogen infrastructure corridor from Finland through Estonia, Latvia, Lithuania and Poland to Germany.

The Nordic-Baltic Hydrogen Corridor project supports the diversification of energy supply and the accelerated introduction of renewable energy. 

The project strongly supports the EU’s hydrogen strategy and the REPowerEU plan. In addition, the hydrogen corridor of the Nordic and Baltic Sea region supports several regional and EU climate goals.

The parties to the project are gas transmission system operators (TSOs): Gasgrid, (Finland), Elering (Estonia), Conexus Baltic Grid (Latvia), Amber Grid (Lithuania), Gaz System (Poland) and ONTRAS (Germany). 

Information about the project in European Commmisssions Transparency platform


The development and construction of the Nordic- Baltic Hydrogen Corridor will be a key enabler for: 

  • Connecting competitive green and low carbon hydrogen supply produced in the Baltic Sea region with supply consumption points and industrial clusters along the Corridor and in Central Europe. 
  • Promoting cooperation and integration among EU countries by development of cross-border hydrogen infrastructure and thereby strengthening common energy markets and improving energy supply security across the region. 
  • Providing Europe with domestic, competitive green H2 supply and ensuring build-out of renewables where it is the most economical and thereby contributing to European targets of providing affordable energy to its citizens. 
  • Improving energy security and diversification of energy supply instead of importing fossil energy to Europe its replaced by domestically produced green and low-carbon energy what makes the EU less vulnerable to geopolitical tensions and energy price fluctuations. 
  • Enhancing market integration and creation of integrated H2 markets around the Baltic Sea to ensure the development of H2 value chains. 
  • Fostering innovation and business opportunities in hydrogen value chains related technologies, services and solutions and thereby accelerating the European wide sustainable growth and development and improving Europe’s position in the global competition  


 


2022

Cooperation agreement between six transmission system operators

PRESS RELEASE

2024

Project obtained an approval by the European Parliament and the Council for their Projects of Common Interest (PCI) status 

2024

Completed pre-feasibility study

PRESS RELEASE

Feasibility study started

PRESS RELEASE

2025

European Commission allocates co-financing for feasibility study

PRESS RELEASE

Grant Agreement with European Climate, Infrastructure and Environment Executive Agency (CINEA) about co-financing of the Study phase signed

PRESS RELEASE

2026

Non-binding Call for Interest launched until 31.03.2026

PRESS RELEASE

Call for Interest results

PRESS RELEASE

 



An environmental impact assessment procedure has been initiated for the North-Baltic Hydrogen Corridor project in accordance with the Law “On Environmental Impact Assessment”. 

On April 2, 2026, AS "Conexus Baltic Grid" submitted a notice of proposed activity to the State Environmental Service (SES).  On April 17, 2026, the SES adopted Decision No. 11.17/AP/3695/2026 on the application of the environmental impact assessment (EIA) procedure to the proposed activity - the construction of the Nordic-Baltic Hydrogen Corridor on Latvian territory. 

Since the planned activity may affect cross-border nature, in accordance with the legislation, information about the planned activity was translated into English and sent to the Lithuanian and Estonian competent authority. 

The initial public consultations were organized from July 28 to September 1, 2026. The presentation from the public discussions meetings can be found here. 

In accordance with the national legislation, on August 19, 2026, AS Conexus Baltic Grid submitted the request to the SES to develop the EIA program for the planned activity and provided information regarding the schedule for the intial public consultation process. On the September 21, 2026, materials concerning the conducted initial public consultation were submitted to the SES and all involved municipalities. The EIA Program for the construction of the Nordic-Baltic Hydrogen Corridor within the territory of Latvia was issued on the 9th October 2026.


 